T5 has published a page about what its Grayslake campus "gives back". Unfortunately, it raises more questions than it answers...
Nothing below disputes T5's arithmetic. Each figure is theirs. What changes is the timeframe and the wording they chose to put around it.
What assumptions were used to calculate $70M/year? What are the other costs incurred and revenue foregone during this 20-year period? If T5 goes bankrupt sometime within the next 20 years, what is Grayslake going to do to collect property taxes? Grayslake will be left scrambling to offload millions of square feet of concrete-reinforced buildings. What is Grayslake's contingency plan if the AI bubble bursts?
Quoted from their page"Up to 1500" jobs: Is that total for each year or total all years? Construction has already started: How many actual local construction jobs are planned for each year, including this year? How many are union and how many non-union? How many of the jobs require special skills? How many permanent jobs will this project create and how many filled by Lake County residents?
Quoted from their pageDid T5 purchase ComEd? Unless it did, ComEd can charge its customers rates necessary to recover the costs of infrastructure investments, including those made to support large-scale data centers like T5 Chicago IV. Therefore, while Grayslake residents may not see a direct line item on their bills for the data center's electricity supply, they will ultimately bear the cost through higher utility rates.
Quoted from their pageComing to Grayslake and Lake County
Here are a few things we'll also be welcoming to the area.

An electrical substation supporting a 1.2 GW hyperscale data center campus typically requires a physical footprint of 650,000 to 1,300,000 square feet (equivalent to 15 to 30 acres). Great background for wedding photos!

To back up 1.2 GW of capacity requires roughly 468 of these diesel backup generators, and they all have to be tested even if they aren't used regularly. Some people actually like the smell of diesel, so there's that. We'll probably get used to it.

To back up 1.2 GW of capacity, assuming 4MW batteries like the Vertiv EnergyCore, there will be 30-1200 of these in a Battery Energy Storage System. Typically these are lithium batteries, and lithium batteries have an interesting feature: When they overheat they can burn, causing a condition called thermal runaway in which they create their own oxygen and generally have to be left to burn for as long as it takes for them to burn out. Look up Moss Landing, CA .

"Up to" sets a ceiling, not a floor, and one job is enough to clear it. And is that up to 1500 new jobs per year or up to 1500 over the entire project lifetime? Their supporting text describes construction work across a 7–10 year build, which ends when the build ends. Are all of those "up to" 1500 those temporary construction jobs? How many full or part time permanent jobs, at what level, and how many filled by Lake County residents?
Quotations from investingingrayslake.com, archived September 3, 2026.
What our neighbors say
PlaceholderA quotation from a named Grayslake or Lake County resident who has agreed in writing to be quoted.
Name hereGrayslake resident
Their answers, unedited
Each grey line is quoted word for word from their FAQ. Each orange line is the question that answer does not settle. We have not shortened or paraphrased anything.
"Will this drain our water?"
This says the cooling system is filled once and then sealed.
"Will my electric bill go up?"
"What about sound?"
"Was the community consulted?"
"What has T5 done to address community concerns about the impact to wetlands?"
Our figures, stated as such
These are our numbers, not theirs, and we show our work. Calculated from the stated facility rating at 60% utilization and a power usage effectiveness of 1.25. If the real configuration differs, these should be corrected — we would welcome the engineering plans that would allow it.